National Highways Authority Of ... vs Bumi Hiway (M) Sdn Bhd on 25 March, 2015

$
0
0

25.03.2015

1. Both these petitions under Section 34 of the Arbitration and Conciliation Act, 1996 (‘Act’) raise limited challenge to an Award dated 4th December 2012 passed by the Arbitral Tribunal (‘AT’) in the disputes between the parties i.e. the National Highways Authority of India (NHAI) and Bhumi Hiway (M) SDN BHD ('BHSB') arising out of a contract agreement dated 14th June 2001 for the Four-Laning of Km 4.23 to 26.00 of Jalandhar Pathankot Section of NH-1A in the State of Punjab.

2. The start date was 30th August 2001. The scheduled date of completion was 29th August 2003. The date up to which the extension was granted was 30th September 2004. In terms of the report of the Engineer the date of substantial completion was 1st October 2004 and the date of completion was 16th October 2004.